The issue
Eneteq Services has installed over 4,000m of district heating transmission pipes as part of the ongoing redevelopment at Wembley Park. They have established the underground heating mains for the entire Wembley Park redevelopment in several phases between 2018 and 2021.
These pipes transfer heat from the purpose-built Combined Heat & Power (CHP) plant to each of the 17 residential blocks for domestic and water heating use. This District Heating (DH) network represents a considerable saving of carbon compared to the traditional model of each residential unit producing its heat and hot water. Before the transmission pipes can be used, they must be carefully cleaned to remove any particulate matter such as swarf or construction residues which could damage the heat exchangers or shorten the life of the pipework.
The traditional method for cleaning these systems is dynamic flushing with side stream filtration, which requires pumping water and chemicals through the network at high velocity for up to two weeks.
The solution
With Ice Pigging™, it is possible to carry out a pre-commissioning clean on a large area of DH pipework in a single day. It can easily be applied using existing fill and drain vents on the network and requires no harmful chemicals.
Eneteq was an early adopter of Ice PiggingTM in the DH sector, with SUEZ providing Ice Pigging™ services for commissioning projects since 2017. Given the high status of the Wembley project and the time constraints associated with such a largescale redevelopment, Eneteq approached SUEZ to clean the entire underground transmission network.
We have used and specified Ice Pigging on all of our larger diameter installations, as the dynamic flushing on these pipes can be incredibly difficult due to the flow rates required. Ice Pigging has proved to be a much simpler method for the dynamic flushing element of the works and it has allowed us to reduce the overall timeline of the commissioning process.Tim Coles , Operations Manager at Eneteq Services Ltd
The results
l/sec